Solar

CERC Approves ₹23.92 Billion Transmission Charges for Khavda 8 GW Renewable Energy Evacuation

CERC has approved ₹23.92 billion in annual transmission charges for the 8 GW Khavda renewable energy evacuation project in Gujarat under Phase-V Part C

EXD Editorial·May 18, 2026

CERC Approves ₹23.92 Billion Transmission Charges for Khavda 8 GW Renewable Energy Evacuation

India's Central Electricity Regulatory Commission (CERC) has approved annual transmission charges of ₹23.92 billion (approximately $249.86 million) for the interstate transmission system (ISTS) project designed to evacuate 8 gigawatts of renewable energy from the Khavda Renewable Energy Zone in Gujarat's Kutch district, under Phase-V: Part C. The ruling marks a pivotal regulatory milestone for one of the largest single-zone clean energy evacuation infrastructure projects ever sanctioned in India. Khavda, already home to what is shaping up to be the world's largest renewable energy park, sits at the heart of India's push to hit its 500 GW non-fossil fuel capacity target by 2030. The CERC order institutionalises the cost framework that will allow power generated at Khavda — from solar, wind, and hybrid projects developed by major players including Adani Green Energy — to flow reliably into the national grid via a robust ISTS backbone, giving developers, lenders, and state distribution companies the regulatory certainty they need to commit capital at scale.

What Does the CERC Order Cover for Khavda Transmission?

The CERC approval specifically addresses the interstate transmission infrastructure required to wheel 8 GW of renewable power out of the Khavda zone under Phase-V: Part C of the broader Khavda evacuation plan. The transmission system, built and operated under the aegis of Power Grid Corporation of India Limited (PGCIL) — India's central transmission utility — involves a complex network of high-voltage direct current (HVDC) and alternating current (AC) lines stretching from Gujarat's arid Rann of Kutch region into load centres across multiple states. By fixing annual transmission charges at ₹23.92 billion, CERC has established a tariff certainty corridor that protects both the transmission developer's revenue stream and the interests of long-term power offtakers. The Phase-V: Part C designation indicates this is a sequential build-out, with earlier phases already at various stages of commissioning, meaning the 8 GW covered here adds to a cumulative evacuation capacity that will eventually handle tens of gigawatts from the Khavda zone alone.

The financial scale of the approved charges — nearly ₹24 billion annually — underscores the infrastructure investment intensity behind India's clean energy ambitions. Transmission bottlenecks have historically been one of the most stubborn barriers to renewable energy integration in India, with projects commissioned but unable to evacuate power due to grid delays. This regulatory clearance signals that the system around Khavda is advancing in lockstep with generation capacity, a coordination that MNRE and the Ministry of Power have prioritised explicitly in their 2030 renewable energy planning documents.

Why Khavda Is Central to India's Solar and Wind Strategy

Khavda, located in the Kutch district of Gujarat, has emerged as India's most strategically significant renewable energy geography. The site spans roughly 72,600 hectares of wasteland — an area larger than Singapore — and is being developed as an integrated renewable energy park targeting an eventual installed capacity of 30 GW or more. Adani Green Energy alone has committed to developing 20 GW at Khavda, and the company has already commissioned several hundred megawatts of solar capacity there, with aggressive commissioning schedules through 2027 and 2028. Gujarat's combination of high solar irradiation, strong wind speeds, flat terrain, and proximity to existing grid infrastructure makes Khavda uniquely suited for utility-scale hybrid generation at costs that are competitive even globally. SECI (Solar Energy Corporation of India) has run multiple auctions tying generation capacity at Khavda to central government offtake, providing the demand-side visibility that anchors transmission investment decisions like the one CERC has now ratified.

For India's broader 500 GW renewable target, Khavda alone could contribute 10 percent of the total installed base — a concentration of capacity in a single geography that is extraordinary by any international benchmark. The CERC transmission charge approval ensures that the power generated there will have a commercially viable and legally defined pathway to market, which in turn de-risks project finance for the gigawatts of solar and wind capacity still under development at the site. Rajasthan's Fatehgarh and Bhadla solar parks have demonstrated what focused state-level policy and transmission co-ordination can achieve; Khavda is designed to replicate and exceed that model.

What This Means for India's Energy Transition

India's 500 GW renewable energy target by 2030 is not just a capacity number — it is an infrastructure and grid integration challenge of the highest order. Every gigawatt of solar or wind generation is only as useful as the transmission network that connects it to demand. The CERC approval of ₹23.92 billion in annual transmission charges for the Khavda 8 GW evacuation project is, in that sense, as important as any generation capacity auction. It signals that India's regulatory architecture is maturing to handle the scale of investment required — providing tariff certainty, protecting grid operators' revenues, and enabling state discoms in destination states to plan procurement. With MNRE pushing hard on renewable energy zones across Rajasthan, Gujarat, Tamil Nadu, Andhra Pradesh, and Karnataka, the Khavda regulatory framework will likely serve as a template for future ISTS approvals tied to large renewable energy parks.

Watch for CERC to issue similar transmission charge orders for subsequent Khavda phases, as well as for ISTS projects linked to Rajasthan's renewable energy zones under the Green Energy Corridor Phase-II. The pace at which PGCIL commissions the physical infrastructure — and whether it stays ahead of generation commissioning timelines — will determine whether India's clean energy transition runs on schedule or accumulates the grid-stranding risk that has plagued past renewable build-outs. The Khavda precedent, now firmly set, is a promising signal.

Key Facts

  • CERC approved annual transmission charges of ₹23.92 billion (~$249.86 million) for Khavda Phase-V Part C ISTS project
  • The project will evacuate 8 GW of renewable energy from Khavda Renewable Energy Zone in Kutch, Gujarat
  • Adani Green Energy is developing 20 GW of renewable capacity at Khavda, which targets a total installed capacity exceeding 30 GW

Frequently Asked Questions

What did CERC approve for the Khavda renewable energy project?

CERC approved annual transmission charges of ₹23.92 billion (approximately $249.86 million) for the interstate transmission system that will evacuate 8 GW of renewable power from the Khavda Renewable Energy Zone in Gujarat under Phase-V: Part C.

How much renewable energy capacity will Khavda ultimately generate?

Khavda Renewable Energy Park in Gujarat's Kutch district is planned to host over 30 GW of solar and wind capacity. Adani Green Energy alone is developing 20 GW there, making it potentially the world's largest single renewable energy site.

Why is transmission infrastructure important for India's 500 GW renewable target?

Without approved and funded transmission infrastructure, renewable energy generated at large parks like Khavda cannot reach consumers. CERC's tariff approvals for ISTS projects ensure grid operators have revenue certainty, enabling timely construction and preventing power from being stranded at the generation site.